Completing the SFHA upgrade on BE on Solaris 11

Last published : Sep 18, 2026
At the end of the process:
  • The alternate BE is activated.
  • The system is booted from the alternate BE.
To complete the BE upgrade
  1. Activate the alternate BE.
    \# beadm activate altroot.7.3
    1. Stop application and VCS on all nodes.
    \# hastop -all
  2. Restart all the nodes in the cluster. The BE on the alternate disk is activated when you restart the nodes.
    Note: Do not use thereboot,halt, oruadmincommands to restart the system. Use either theinitor theshutdowncommands to enable the system to boot using the alternate BE.
\# shutdown -g0 -y -i6
  1. If you want to upgrade the CP server systems that use VCS or SFHA to this version, make sure that you upgrade all application clusters to this version. Then, upgrade VCS or SFHA on the CP server systems.
For instructions to upgrade VCS or SFHA on the CP server systems, see the VCS or SFHA Installation Guide.