Adding the node to a cluster manually

Last published : Jun 10, 2026
Perform this procedure after you install Veritas InfoScale Enterprise only if you plan to add the node to the cluster manually.

Table: Procedures for adding a node to a cluster manually

Step Description
Start the Veritas Volume Manager (VxVM) on the new node. See Starting Veritas Volume Manager (VxVM) on the new node .
Configure the cluster processes on the new node. See Configuring cluster processes on the new node .
Configure fencing for the new node to match the fencing configuration on the existing cluster. See Starting fencing on the new node .
If the existing cluster is configured to use server-based I/O fencing, configure server-based I/O fencing on the new node.
Start VCS. See “To start VCS on the new node” .
If the ClusterService group is configured on the existing cluster, add the node to the group. See Configuring the ClusterService group for the new node .