Configuring a new Veritas InfoScale Operations Manager installation in high availability environment

Last published : Jun 19, 2026
You can configure Veritas InfoScale Operations Manager in high availability environment immediately after the initial configuration of Management Server. In this method, you do not have to change the host name and the IP address of the host.
Note: To avoid losing the data, do not use this method to configure high availability environment on an existing Management Server. Follow the process of configuring an existing Veritas InfoScale Operations Manager installation in high availability environment.
Configuring a new Veritas InfoScale Operations Manager installation in high availability environment involves the following steps:

Table: Configuring a new Veritas InfoScale Operations Manager installation in high availability environment

Step Action Description
1 Ensure the prerequisites for configuring a new Management Server installation in high availability environment. See Prerequisites for configuring a new Management Server in high availability environment .
2 Perform initial configuration of Management Server installation in high availability environment. See Performing initial configuration of Management Server in HA environment .
3 Create the base service groups in VCS. See Creating the base service groups for HA configuration .
4 Complete the configuration of a Management Server installation in high availability environment. See Completing the configuration of a Management Server installation in HA environment .
More Information