Configuring Management Server in one-to-one DR environment

Last published : Aug 24, 2026
Following is an overview of the process of configuring Management Server in one-to-one symmetrical DR environment:
  • Install Management Server on the local cluster (Node1) and the remote cluster (Node2).
  • Configure Management Server on Node1 only.
  • Add Node2 as a managed host to the Management Server that is configured on Node1. Node1 at the local cluster acts like the primary site while Node2 at the remote cluster acts like the secondary site.
  • Replicate the Veritas InfoScale Operations Manager database and the domain-wide information that is stored in the shared storage to the secondary node. You can use Replicator Option (VVR) to replicate the data on the secondary node.
  • In case of a failover, the primary node fails over to the secondary node.
To perform this task, you must have a root user account or your user group must be assigned the Admin role on the Management Server perspective.
Configuring a Veritas InfoScale Operations Manager installation in disaster recovery environment involves the following steps:

Table: Configuring a Veritas InfoScale Operations Manager installation in disaster recovery environment

Step Action Description
1 Ensure the prerequisites for configuring a Management Server installation in disaster recovery environment. See Prerequisites for configuring a Management Server in Symmetrical DR environment .
2 Perform initial configuration of Management Server installation in disaster recovery environment. See Performing initial configuration of Management Server installation in DR environment .
3 Create the base service groups in VCS for DR configuration. See Creating the base service groups for DR configuration .
4 Enable Veritas InfoScale Operations Manager DR configuration. See Enabling DR configuration .
More Information